Aug 31

Cove Blvd Work on Schedule

Posted on August 31, 2018 at 1:00 PM by Eric Cottingham

For the week of September 3, 2018 the remaining roadway surface will be recycled and prepared for paving. Guardrail will be installed and pavement will be placed between Royal Coachman Blvd and Cove Condos. The roadway is scheduled to reopen at the end of the week, weather permitting.

No work will take place over the Labor Day week-end holiday. Detours will remain in place throughout the week.

Please be cautious when walking, biking, or driving through the work zone. Thank you, as always, for your patience and cooperation during this construction.